Laise

Guide · 6 min read · Updated 12 Nov 2026

Bid security, bid bonds and performance guarantees explained

What bid security and performance bonds are, why buyers demand them, how to obtain one from a bank or insurer, and the mistakes that get bids rejected.

Many public tenders, especially for works and larger supply contracts, require financial guarantees from bidders. They protect the buyer if a bidder walks away or a contractor fails to perform. They are also one of the most common causes of rejected bids, because a guarantee that is slightly wrong counts as no guarantee at all.

Bid security

Bid security, also called a bid bond or tender guarantee, is submitted with your bid. It promises that you will keep your offer open for the stated validity period and sign the contract if you win. If you withdraw or refuse to sign, the buyer can claim the amount. It is usually a fixed sum or a small percentage of the bid price, commonly between one and three percent. Some tenders accept a signed bid-securing declaration instead, which costs nothing but can lead to a ban from future tenders if broken.

Performance security

The winning bidder provides performance security, or a performance bond, before or at contract signature. It covers the buyer against failure to deliver and is typically five to ten percent of the contract value, held until completion or the end of the defects period.

Advance payment and retention guarantees

Where a contract pays an advance, the buyer normally asks for an advance payment guarantee of the same amount, reducing as the advance is recovered. Some contracts also let you replace cash retention with a retention guarantee, which improves your cash flow.

How to obtain one

  • Approach your bank or an insurer licensed to issue bonds as soon as you decide to bid. First-time applications can take a week or more.
  • Expect to provide the tender documents, company accounts and security such as a cash margin or a charge over assets.
  • Budget for the fee, usually a percentage of the guarantee amount for each quarter or year it is in force.
  • Give the issuer the exact wording required. Most tenders include a mandatory template.

Mistakes that get bids rejected

  • Wrong amount or currency.
  • Validity that ends before the date the tender requires, often the bid validity period plus 28 or 30 days.
  • Issued by an institution the tender does not accept.
  • Wording changed from the buyer's template, or made conditional.
  • Name of the bidder or the buyer written incorrectly, or a joint venture guarantee issued in the name of only one partner.
  • A copy submitted where the original was required.

Getting your security back

Bid securities of unsuccessful bidders are returned after the contract is signed or the bid validity expires. If you are asked to extend your bid validity, you will also need to extend the security, and you are entitled to refuse the extension without losing it.

Live examples

Open tenders right now

See all

FAQ

Frequently asked questions

How much is a bid bond?

The tender documents state the amount. It is usually a fixed sum or between one and three percent of the bid price. The cost to you is the issuer's fee, which is a small percentage of that amount, plus any cash margin your bank holds.

What is a bid-securing declaration?

It is a signed statement, used in place of a bank guarantee, in which the bidder accepts being suspended from future tenders if they withdraw their bid or refuse to sign the contract. Many development bank tenders allow it for smaller contracts.

What is the difference between a bid bond and a performance bond?

A bid bond covers the tender stage and guarantees that you will honour your bid. A performance bond is provided by the winner and guarantees that the contract will be delivered.